Zurich

Network fit-out and staff relocation

30 people

Fit-out

floorplan designs

construction

mechanical

electrical

lighting

New Installation

LAN cabling

LAN hardware

WAN

telephony

desktop PCs

audio-visual

security

furniture

Relocation

LAN hardware

telephony

servers

desktop PCs

staff

I was asked to help with an office relocation in Zurich, amalgamating staff from two floors the client wanted to return to the landlord, to a new floor in the same building, the client had rented.

 

The move required installing new LAN hardware on the new floor and connecting it to the existing LAN on remaining floors, inter-floor copper and fibres, patching about 80 positions and relocating approximately 30 members of staff.

 

The IT fit-out and staff move was completed on schedule.

 